6. Decision Mathematics
Critical Path — Quiz
Test your understanding of critical path with 5 practice questions.
Practice Questions
Question 1
What is the term for the earliest time an activity can begin without delaying the project?
Question 2
If an activity has a duration of 7 days and its Latest Finish Time (LFT) is 15 days, what is its Latest Start Time (LST)?
Question 3
Which of the following is NOT a typical component of a project activity network diagram?
Question 4
In Critical Path Analysis, what does a zero slack value for an activity signify?
Question 5
What is the primary purpose of a forward pass in Critical Path Method (CPM)?