5. Decision Mathematics
Critical Path — Quiz
Test your understanding of critical path with 5 practice questions.
Practice Questions
Question 1
In CPM analysis, an activity for which $EF = LF$ always has which characteristic?
Question 2
Consider the project network where Activity $A$ (3 days) precedes both $B$ (4 days) and $C$ (6 days) in parallel, and both $B$ and $C$ precede Activity $D$ (5 days). Which sequence constitutes the critical path and what is the project duration?
Question 3
For the network described above, what is the total float of Activity $B$?
Question 4
In the same network, what is the free float of Activity $C$?
Question 5
In a backward pass, if Activity $E$ has duration 5 days and its only successor $F$ has latest start $LS_F = 10$ days, what are $LF_E$ and $LS_E$?