Contract Documents — Quiz
Test your understanding of contract documents with 5 practice questions.
Practice Questions
Question 1
A contract includes a liquidated damages clause of $1\,000$ per day. If the contractor achieves substantial completion 15 days late, what is the total liquidated damages owed?
Question 2
If the contract sum is $1\,200\,000$ and the General Conditions specify a retainage of 5% to be withheld from progress payments, how much retainage is withheld initially?
Question 3
Which document is issued by the architect to authorize minor changes in the work that do not alter the contract sum or time?
Question 4
Which of the following documents is part of the Bidding Requirements in the Project Manual?
Question 5
In the hierarchy of contract documents, if a clause in the Supplementary Conditions conflicts with the Standard General Conditions, which document governs?