5. Project Controls
Earned Value — Quiz
Test your understanding of earned value with 5 practice questions.
Practice Questions
Question 1
What does the Performance Measurement Baseline (PMB) represent in Earned Value Management?
Question 2
If Planned Value (PV) is \120{,}000, Earned Value (EV) is \100{,}000, and Actual Cost (AC) is \110{,}000, what is the Cost Variance (CV) and its interpretation?
Question 3
Given PV = \$80{,}000, EV = \$70{,}000, and AC = \75{,}000, what are the Cost Performance Index (CPI) and Schedule Performance Index (SPI), and what do they indicate?
Question 4
Which Estimate at Completion (EAC) formula should be used when future work is expected to be completed at the original budgeted rate regardless of past performance?
Question 5
If Budget at Completion (BAC) is \200{,}000, Earned Value (EV) is \120{,}000, and Actual Cost (AC) is \150{,}000, what is the To-Complete Performance Index (TCPI) to achieve BAC and what does a TCPI >1 signify?
