5. Project Controls
Forecasting Techniques — Quiz
Test your understanding of forecasting techniques with 5 practice questions.
Practice Questions
Question 1
Which forecasting technique involves creating multiple possible future scenarios to assess potential outcomes and risks in a construction project?
Question 2
A construction project has a 'Budget at Completion' (BAC) of $3,000,000$. The 'Earned Value' (EV) is $1,200,000$ and the 'Actual Cost' (AC) is $1,500,000$. What is the 'Estimate at Completion' (EAC) if the current 'Cost Performance Index' (CPI) is expected to continue?
Question 3
In the context of schedule forecasting, what does a 'Schedule Performance Index' (SPI) of $0.9$ signify?
Question 4
Which of the following is a primary characteristic of short-term forecasting in construction management?
Question 5
A construction project has an 'Earned Value' (EV) of $180,000$, a 'Planned Value' (PV) of $200,000$, and an 'Actual Cost' (AC) of $190,000$. What is the 'Schedule Variance' (SV) and 'Cost Variance' (CV) for this project?