5. Project Controls

Progress Measurement — Quiz

Test your understanding of progress measurement with 5 practice questions.

Read the lesson first

Practice Questions

Question 1

Which progress measurement technique uses standard labor hours per unit and actual quantity installed to calculate percent complete?

Question 2

If a construction activity has a Planned Value (PV) of \120,000 and an Earned Value (EV) of \$90,000, what is the Schedule Variance (SV)?

Question 3

A project has a Budget at Completion (BAC) of \500,000. To date, the Earned Value (EV) is \275,000 and the Actual Cost (AC) is \$250,000. What is the Cost Performance Index (CPI)?

Question 4

What is the primary purpose of a look-ahead schedule in construction progress measurement?

Question 5

In complex construction projects, what advantage do weighted milestones offer over units completed methods?
Progress Measurement Quiz — Construction Management | A-Warded