5. Project Controls
Progress Measurement — Quiz
Test your understanding of progress measurement with 5 practice questions.
Practice Questions
Question 1
Which progress measurement technique uses standard labor hours per unit and actual quantity installed to calculate percent complete?
Question 2
If a construction activity has a Planned Value (PV) of \120,000 and an Earned Value (EV) of \$90,000, what is the Schedule Variance (SV)?
Question 3
A project has a Budget at Completion (BAC) of \500,000. To date, the Earned Value (EV) is \275,000 and the Actual Cost (AC) is \$250,000. What is the Cost Performance Index (CPI)?
Question 4
What is the primary purpose of a look-ahead schedule in construction progress measurement?
Question 5
In complex construction projects, what advantage do weighted milestones offer over units completed methods?