6. Design and CAD

Capstone Project — Quiz

Test your understanding of capstone project with 5 practice questions.

Read the lesson first

Practice Questions

Question 1

Which document identifies all project stakeholders and their interests?

Question 2

When using a decision matrix to select a design concept, which step assigns relative importance to evaluation criteria?

Question 3

For a PERT activity with optimistic duration O=3 days, most likely M=5 days, and pessimistic P=9 days, what is the expected duration $T_E$?

Question 4

A project has BCWS=\$20 000, BCWP=\$18 000, and ACWP=\$22 000. What is the cost variance (CV)?

Question 5

What is the primary purpose of Monte Carlo simulation in project scheduling?
Capstone Project Quiz — Mechanical Engineering | A-Warded