Capstone Project — Quiz
Test your understanding of capstone project with 5 practice questions.
Practice Questions
Question 1
Which document identifies all project stakeholders and their interests?
Question 2
When using a decision matrix to select a design concept, which step assigns relative importance to evaluation criteria?
Question 3
For a PERT activity with optimistic duration O=3 days, most likely M=5 days, and pessimistic P=9 days, what is the expected duration $T_E$?
Question 4
A project has BCWS=\$20 000, BCWP=\$18 000, and ACWP=\$22 000. What is the cost variance (CV)?
Question 5
What is the primary purpose of Monte Carlo simulation in project scheduling?