6. Project and Service Ops
Critical Path — Quiz
Test your understanding of critical path with 5 practice questions.
Practice Questions
Question 1
Which statement best distinguishes total float from free float in CPM scheduling?
Question 2
If an activity in a CPM network has zero total float, it implies that the activity...
Question 3
What does critical path drag measure in project management?
Question 4
Three sequential activities A, B, and C have optimistic, most likely, and pessimistic durations as follows: A: $o=3,m=5,p=9$ days; B: $o=2,m=4,p=6$ days; C: $o=1,m=3,p=5$ days. Assuming they form the critical path, what is the expected project duration $T_E$?
Question 5
Using the same activities in the previous question, what is the variance $\sigma^2$ of the project duration?