3. Property Development
Design Management — Quiz
Test your understanding of design management with 5 practice questions.
Practice Questions
Question 1
In design management, what is a Common Data Environment (CDE)?
Question 2
What is the purpose of a BIM Execution Plan (BEP) in a design project?
Question 3
If a project has a base design cost of \\$1,200,000 with a design contingency rate of 5\\% and a project contingency rate of 3\\%, what is the total contingency amount?
Question 4
Which resource management technique extends the overall project duration to avoid resource over-allocation?
Question 5
Which resource management technique delays non-critical tasks within their slack time without changing the project end date?